Why Dutch Housing Construction Projects Are Taking Longer to Complete
Housing construction in the Netherlands is facing unprecedented delays. According to Statistics Netherlands (CBS), the average time from permit issuance to the delivery of a new home has extended to nearly two years, up from 1.5 years just ten years ago. These growing timelines are especially pronounced in urban regions, affecting the supply of new homes at a time when demand remains strong.
Permit to Completion: A Growing Timeline
Recent CBS data shows that of the homes completed in the first three quarters of 2025:
- 50% had their first building permit issued less than 23 months ago.
- The fastest 25% of projects wrapped up in under 16 months.
- The slowest 25% required over 35 months to complete.
By contrast, in 2015, half of all new homes were delivered within 16 months of permit approval, and 75% within 25 months. This shift underscores how construction has slowed across the board—not just in housing but also in schools, offices and shops (now 20 months on average, compared to 15 months a decade ago).
Regional Variations: From Overijssel to North Holland
Not all provinces experience the same delays. CBS reports the following average completion times for homes in 2025:
- Noord-Holland: 26 months (slowest)
- Zuid-Holland: 22 months
- Utrecht: 21.5 months
- Overijssel: 15 months (fastest)
These disparities reflect differences in municipal processes, labour availability, and the complexity of local projects. Highly urbanized regions tend to see longer permitting processes, denser development patterns, and higher demand for specialized contractors.
Urban Versus Non-Urban: Complexity Drives Delays
Construction in cities is particularly time-consuming. CBS highlights that in urban municipalities:
- Apartment buildings average 28.6 months from permit to handover.
- Single-family homes average 19.6 months.
In contrast, non-urban areas complete apartment buildings in 19.9 months and single homes in 15.2 months. The added complexity of high-rise construction, tighter building sites, and more stringent safety regulations in cities contribute to these extended timelines.
Key Factors Behind Extended Construction Times
Several interrelated factors are driving these slowdowns:
-
Permit and Zoning Complexities
Municipalities are tightening zoning rules and environmental assessments, adding months to application and review processes. -
Labour Shortages
The construction industry faces skilled labour shortages—in carpentry, plumbing and electrical work—which slow project schedules and push up costs. -
Supply Chain Disruptions
Global material shortages and shipping delays for steel, timber and insulation have increased lead times for critical components. -
Sustainability Requirements
New energy performance standards (e.g., near-zero energy buildings) demand advanced materials and specialized installation, which can lengthen construction phases. -
Complex Urban Sites
Building in densely populated areas often involves difficult logistics—limited staging space, night-time work restrictions and elaborate safety plans.
Impacts on the Rental Market and Tenants
Longer construction timelines have downstream effects on renters:
- Tighter Supply: Delays in new builds reduce the influx of fresh rental units, exacerbating shortages in hot markets like Amsterdam and Utrecht.
- Rising Rents: Lower supply pushes average rents higher, with professional landlords passing on increased building costs and financing charges.
- Extended Waiting Lists: Woningcorporaties (social housing associations) face longer applicant queues as new social rental homes also arrive later.
For internationals and expats searching the Dutch rental market, these delays mean fewer options and stiffer competition for available properties.
How to Navigate the Delayed Market
While systemic changes take time, tenants and prospective renters can take steps to improve their chances:
- Broaden Your Search Area: Consider neighbouring towns or less urbanised municipalities where new projects complete faster.
- Register Early: Sign up with woningcorporaties and rental platforms like Luntero to receive alerts when new listings go live.
- Prepare Documentation: Have proof of income, references and a rental portfolio ready to speed up your application.
- Be Flexible on Timing: If you need a home within months, look for existing stock rather than waiting for new builds.
Looking Ahead: Solutions to Speed Up Delivery
Industry experts and policymakers are exploring ways to reduce construction timelines:
- Digital Permitting: Streamlined online application portals can cut bureaucratic delays.
- Modular Construction: Factory-built modules assembled on-site can accelerate overall schedules.
- Training Initiatives: Expanding vocational programs to address the labour gap in trades.
- Public–Private Partnerships: Municipalities collaborating with developers to fast-track priority housing projects.
If these measures gain traction, we could see meaningful reductions in the permit-to-completion cycle over the next five years.